花岗岩残积土地层基坑降水技术研究

  

  • 出版日期:2021-06-01 发布日期:2021-07-19

Problems Induced by Improper Dewatering of Foundation Pit in Granite Residual Soil Layer and Disposal Measures

  • Online:2021-06-01 Published:2021-07-19

摘要: 花岗岩风化残积土具有特殊的工程特性,其遇水后容易导致土体强度丧失、软化、崩解,引发地质灾害,常常给工程建设带来巨大的风险和经济损失。本文结合工程实例,通过理论计算和现场监测结果对比分析,对花岗岩残积土地区基坑降水和分步开挖带来的影响进行了研究,得出了应适当增加止水帷幕深度、预埋注浆管、加强降水管理和及时封底等结论,对广州地铁的工程建设具有一定的指导意义,也为其他城市类似条件下的地铁基坑建设提供参考。

Abstract: Granite weathered residual soil has special engineering characteristics. It will easily lead to the loss of strength, softening and disintegration of the soil body when exposed to water, causing geological disasters, and often bringing huge risks and economic losses to engineering construction. In this paper, combined with engineering examples, through theoretical calculations and comparative analysis of on-site monitoring results, the impact of dewatering and step-by-step excavation of foundation pits in the granite residual soil area is studied, and it is concluded that the depth of the water-stop curtain and the pre-embedded Conclusions such as slurry pipe, strengthening of precipitation management and timely back cover have certain guiding significance for the construction of Guangzhou Metro, and also provide references for the construction of subway foundation pits under similar conditions in other cities.